Obtain Sewerage Connection

Procedure

  • Application form
  • Self attested copy of occupation certificate issued.
  • Certificate from a plumber registered with the Authority
  • Demand Draft towards road cutting charges, if any.
  • In case of an unauthorized sewer connection, additional compounding fee shall be applicable.

Download Booklet

Time limit: – 05 working days from the date of receipt of application.

NOTE: It would be preferred to print on A4 sheet.

Comments for this post are closed.

Ongoing Projects backup

Sr. No. Name of work Estimated cost ( In lac) 1. Special repair of roads with 50mm thick B.M. and 20mm mix seal Type-Bin …